Summer
2004: Renovation
work continues to progress at the junior high school.
The demolition process has occurred in all the third floor
classrooms that were not renovated during Phase 1.
The majority of the electrical, HVAC, and plumbing rough-in
work has also been completed in this area, and the contractor is in
the process of installing the new wallboard.
The remaining rooms to be renovated on the second floor have
been cleaned out and demolition recently started there, as well.
Work in the kitchen is also underway. The existing kitchen has
been completely gutted and old plumbing drain lines, outdated
electrical wiring, and floor tiles have been removed.
The exterior block wall for the pool area is completed, and the
steel beams for the classroom additions at the cafeteria patio have
been put in place. The
block walls will follow.
Work continues on
the exterior of the building, which includes re-roofing, removal of
existing wall panels, and installation of the stone and brick.
Work in the following areas will be completed prior to the
start of school on September 1, 2004:
The
four-story addition at the cafeteria patio
All
stairwells
Cafeteria/kitchen
Two Family
Consumer Science rooms
Lifeskills
room
All of
second and third floors (except the auditorium balcony)
All
exterior windows/exterior
work at the ground level at all entrances and exits
Gas/sanitary
lines/storm drainage/waterline
Electric/phone/cable--service
Work in the
current office space has also begun.
The main office and guidance office staff have been relocated
to the Horace Mann Elementary School for the summer while the
contractors work in these areas.
Please note that the phone number for the junior high school
has not changed.